The Class Q prior approval scheme is a part of the United Kingdom's planning regulations that allows the conversion of agricultural buildings into residential dwellings without the need for full planning permission. This scheme falls under the permitted development rights, specifically under Part 3, Class Q of the Town and Country Planning (General Permitted Development) (England) Order 2015.
The scheme aims to facilitate the reuse of redundant or underused agricultural buildings, promoting rural housing and reducing the pressure to build new homes on greenfield sites.
Eligibility Criteria:
- The building must have been used solely for agricultural purposes on or before 20th March 2013.
- The total floorspace for conversion must not exceed 465 square meters.
- The building must be structurally sound and capable of conversion without significant structural alterations.
Limitations:
- The development cannot extend beyond the existing external dimensions of the building.
- No more than 3 dwellings can be created from a single agricultural unit if the cumulative floorspace exceeds 100 square meters; otherwise, up to 5 smaller dwellings are permitted.
- Certain locations are excluded, such as sites within Areas of Outstanding Natural Beauty (AONB), National Parks, or conservation areas.
Prior Approval Process:
- Even though full planning permission is not required, developers must apply for prior approval from the local planning authority (LPA).
- The LPA assesses various factors including the transport and highways impact, noise impact, contamination risks, flooding risks, and whether the location or siting makes the building impractical or undesirable for residential use.
- Structural integrity and the design and external appearance of the building are also considered.
Application:
- An application for prior approval should include detailed plans and supporting documents demonstrating compliance with Class Q conditions.
- The LPA has a 56-day period to make a decision. If no decision is made within this time frame, the development can proceed by default.
- Facilitates the creation of new homes in rural areas without extensive bureaucratic hurdles.
- Encourages the reuse and conservation of existing buildings, preserving the rural character and reducing environmental impact.
Challenges:
- Ensuring the converted buildings are suitable for residential use without compromising structural safety.
- Balancing rural development with the preservation of natural landscapes and local ecosystems.
[edit] Related articles on Designing Buildings.
- Alterations to existing buildings.
- Article 4 direction.
- Change of use class.
- Class Q permitted development.
- Class R prior approval scheme.
- Class S prior approval scheme.
- CLC calls for rethink of permitted development rights.
- Conservation area.
- Enforcement notice.
- Established use certificate.
- IHBC responds to supporting defence infrastructure and the future of time-limited permitted development rights.
- Lawful development certificate.
- Listed building.
- Local development order.
- National planning policy framework.
- Permitted development: The end of the high street or a blessing in disguise?
- Planning enforcement.
- Planning permission.
- Prior approval.
- Renovation.
- Section 215.
- Sui generis.
- Town and Country Planning Act.
- Town and Country Planning (General Permitted Development) (Amendment) (England) Order.
- Use class.
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.